Fire Station Roundabout and Midland Road Love Lane Junction. Update No. 5 – January 2025

Midland Road Resurface January 2025

Midland Road / Love Lane Junction

The required improvements works to Midland Road and the Love Lane/Chesterton Lane junction were complete before Christmas, with resurfacing and white line painting taking place overnight in January.

All traffic management measures have been removed from these areas.

We hope local businesses and residents will benefit from the improved layout.

Main Fire Station Roundabout Works

Work to the main roundabout closest to the Fire Station is progressing. Safe removal of asbestos in the early stages had caused some initial delays. As work progressed Montel have also needed to relocate some utilities.

However, an attenuation pond is being created under challenging weather conditions. Works to the inner lane of the roundabout and improvements to the splitter lanes on entry and exit are underway and progressing well.

It is currently anticipated that the completion of the works to the main roundabout will move to Summer 2025. We will provide further updates each month.

Contacts

Please use the following details to direct your queries about the infrastructure works. While we do post updates to social media, our email and phone details outlined below will always be the best way to discuss details and raise questions.

Fire Station Roundabout Works

Traffic management issues should be reported by phone to:

01564 700241

This number is monitored 24 hours.

Or email: contact@montel-group.com

Eastern Access Works

If you have any concerns about work being carried out on site for the Eastern Access Road, please contact Montel’s Project Manager:

Mr Steve Draper

07918 767 879

steve.draper@montel-group.com

The Steadings and Bathurst Development

You can also contact The Steadings BDL team if you have any queries about the infrastructure works, or wider queries about the new neighbourhood for Cirencester.

community@thesteadingscirencester.co.uk

0800 002 9055

Further Updates

Further updates will be posted to the News Section of our website in due course.