Eastern Access Road
Within the second phase, the Eastern Access Road is now complete through Parcels 2A, 2B and 2C. Work is expected to begin (subject to planning) on the next section of this road through Parcels 2D and 2E later this year.
The road follows two gentle bends as it graduates up the hill, which gives a welcoming vista whilst also helping to control traffic speed when in use on completion of the development.
The street light connections are in place along with signage. Planting of large trees along the access road is also complete, with secondary planting currently taking place.
Landscaping of the Green Spaces


The footpath through the northern green space will receive its final surface in Summer 2025. Tree and shrub planting has also taken place in this area.
The amphitheatre stones have been laid and planting for this area is planned to take place in the Spring 2025.
Fire Station Roundabout Improvement Works

Work is progressing well. The drainage works within the new roundabout are complete, with further works to the pond progressing well.
During March 2025, new kerbs are being installed on the inside of the roundabout and the new carriageway created will be surfaced.
Note: There will be overnight road closures with diversions in place on the Fire Station roundabout:
Monday 24 March 2025 to Friday 4 April 2025
From 20.00 to 06.00
Excluding Saturday and Sunday nights
Any queries on these overnight closures should be directed by email to: contact@montel-group.com
Contacts
Please use the following details to direct your queries about the infrastructure works. While we do post updates to social media, our email and phone details outlined below will always be the best way to discuss details and raise questions.
Fire Station Roundabout Works
Traffic management issues should be reported by phone to:
01564 700241
This number is monitored 24 hours.
Or email: contact@montel-group.com
Eastern Access Works
If you have any concerns about work being carried out on site for the Eastern Access Road, please contact Montel’s Project Manager:
Mr Steve Draper
07918 767 879
The Steadings and Bathurst Development
You can also contact The Steadings BDL team if you have any queries about the infrastructure works, or wider queries about the new neighbourhood for Cirencester.
community@thesteadingscirencester.co.uk
0800 002 9055
Further Updates
Further updates will be posted to the News Section of our website in due course.